Software Project Scheduling with Multitasking

Submitted
October 24, 2026

Abstract

In software development projects, employees tend to switch between various tasks within a time period. In addition, the task duration usually depends on the number of the allocated employees and their skill levels. We investigate the software project scheduling problem with multitasking and variable durations (SPSPM). We present a non -linear optimis ation model that is then linearised into an equivalent mixed -integer linear programming model. To efficiently solve the NP -hard SPSPM, we design a two -stage priority rule-based heuristic algorithm and an improved genetic algorithm (GA). Extensive computational experiments are conducted on a benchmark dataset consisting of 540 project instances. The parameter settings of the GA are determined based on the Taguchi method for the Design of Experiment. The computational results obtained by comparing our algorithms with the exact solver CPLEX reveal that our GA is effective and competitive.

References

  1. [1] Alba, E., Chicano , J.F. (2007) , Software project management with Gas .
  2. Information Sciences, 177(11), 2380-2401;
  3. [2] Browning, T. R., Yassine, A. A. (2010), Resource-constrained multi-project
  4. scheduling: Priority rule performance revisited . International Journal of
  5. Production Economics, 126(2), 212-228;
  6. [3] Crawford, B., Soto , R., Johnson , F., Monfroy, E., Paredes , F. (2014), A
  7. max-min ant system algorithm to solve the software project scheduling
  8. problem. Expert Systems with Applications, 41(15), 6634-6645;
  9. [4] Demeulemeester, E., Vanhoucke, M., Herroelen, W. (2003), RanGen: A
  10. random network generator for activity -on-the-node networks . Journal of
  11. scheduling, 6(1), 17-38;
  12. [5] Hauder, V .A., Beham, A., Raggl, S., Parragh, S.N., Affenzeller, M. (2020),
  13. Resource-constrained multi -project scheduling with activity an d time
  14. flexibility. Computers & Industrial Engineering, 150, 106857;
  15. [6] Huang, H.C., Lee, L.H., Song, H., Eck, B.T. (2009) , SimMan – A
  16. simulation model for workforce capacity planning. Computers & Operations
  17. Research, 36(8), 2490-2497;
  18. [7] Kazemipoor, H., Tavakkoli-Moghaddam, R., Shahnazari -Shahrezaei, P.,
  19. Azaron, A. (2013) , A differential evolution algorithm to solve multi -skilled
  20. project portfolio scheduling problems. The International Journal of Advanced
  21. Manufacturing Technology, 64(5), 1099-1111;
  22. [8] Kolisch R., Heimerl C. (2012) , An efficient metaheuristic for integrated
  23. scheduling and staffing it projects based on a generalized minimum cost
  24. flow network. Naval Research Logistics, 59(2), 111-127;
  25. [9] Li, H., Hu, Z., Zhu, H., Liu, Y. (2021) , Preemptive resource leveling in
  26. projects. Economic Computation and Economic Cybernetics Studies and
  27. Research, 55(4), 51-68;
  28. [10] Li H., Womer K. (2009) , Scheduling projects with multi -skilled personnel
  29. by a hybrid milp/cp benders decomposition algorithm. Journal of Scheduling,
  30. 12(3), 281;
  31. [11] Li, H., Xiong, L., Liu, Y., Li, H. (2018) , An effective genetic algorithm for
  32. the resource levelling problem with generalised precedence relations .
  33. International Journal of Production Research, 56(5), 2054-2075;
  34. [12] Li, H., Zhang, X., Sun, J., Dong, X. (2020) , Dynamic resource levelling in
  35. projects under uncertainty . International Journal of Production Research ,
  36. 1-21;
  37. Hongbo Li, Hanyu Zhu, Linwen Zheng, Yinbin Liu
  38. ____________________________________________________________
  39. 170
  40. [13] Liu, Y., Hu, Z., Li, H., Zhu, H. (2019) , Does preemption lead to more
  41. leveled resource usage in projects? a computational study based on mixed -
  42. integer linear programming . Economic Computation and Economic
  43. Cybernetics Studies and Research, 53(4), 243-258;
  44. [14] Luna F., González -álvarez, D. L., Chicano , F., Vega-Rodríguez, M.A.
  45. (2014), The software pro ject scheduling problem: a scalability analysis of
  46. multi-objective metaheuristics. Applied Soft Computing, 15(2), 136-148.;
  47. [15] Maenhout, B., Vanhoucke, M. (2016), An exact algorithm for an integrated
  48. project staffing problem with a homogeneous workforce . Journal of
  49. Scheduling, 19(2), 107-133;
  50. [16] Minku L.L., Sudholt, D., Yao, X. (2014), Improved evolutionary algorithm
  51. design for the project scheduling problem based on runtime analysis . IEEE
  52. Transactions on Software Engineering, 40(1), 83-102;
  53. [17] PMI (Project Management Institute). (2016), Pulse of the profession 2016:
  54. The high cost of low performance;
  55. [18] Standish Group. (2015) , CHAOS Report , 2015,
  56. http://www.standishgroup.com;
  57. [19] Xiao, J., Ao , X. T., Tang , Y. (2013), Solving software project scheduling
  58. problems with ant colony optimization. Computers & Operations Research ,
  59. 40(1), 33-46.

Similar Articles

21-30 of 355

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)