A New Approach for Multi-Scenario Project Cash Flow Analysis Based on TODIM and Critical Chain Methods under Grey Uncertainty

DOI:
https://doi.org/10.24818/18423264/54.2.20.16
Submitted
October 24, 2026

Abstract

Prognosticating and monitoring the financial conditions of the projects in terms of the cash are crucial to be considered for companies. Generating reliable cash flow is essential for taking proper decisions and having effective financial control . Furthermore, if the inherent uncertaint ies in projects are not addressed, they could lead to tremendous rates of projects failure and bankruptcy. Thus, it is crucial to consider the i mprecision in projects. Therefore, the objective of this study is to anticipate the projects cash flow. In this paper, a novel approach is proposed to generate the project cash flow by applying both two extensions of critical chain project management and TODIM ( an acronym in Portuguese for interactive Multi -Criteria Decision Making (MCDM)) method under grey -environments. Therefore, grey numbers are empl oyed to state the uncertainty of activity durations, qualities, and costs. Finally, a real -world construction project is utilized to demonstrate the applicability and efficiency of proposed approach.

References

  1. [1] Bazilevych, K., Mazorchuk, M., Parfeniuk, Y., Dobriak, V., Meniailov, I.,
  2. &Chumachenko, D. (2018), Stochastic Modelling of Cash Flow for
  3. Personal Insurance Fund Using the Cloud Data Storage.International
  4. Journal of Computing, 17(3), 153-162;
  5. [2] Bhattacharyya, R. (2015), A Grey Theory Based Multiple Attribute
  6. Approach for R&D Project Portfolio Selection.Fuzzy Information and
  7. Engineering, 7(2), 211-225;
  8. Seyed Ali Mirnezami, Seyed Meysam Mousavi, Jurgita Antucheviciene,
  9. Vahid Mohagheghi
  10. __________________________________________________________________
  11. 278
  12. DOI: 10.24818/18423264/54.2.20.16
  13. [3] Chen, C. H., Ling, S. F. & Chen, W. (2003), Project Scheduling for
  14. Collaborative Product Development Using DSM.International Journal of
  15. Project Management, 21(4), 291-299;
  16. [4] Davoudabadi, R., Mousavi, S.M., Šaparauskas, J.&Gitinavard H.
  17. (2019),Solving Construction Project Selection Problem by a New Uncertain
  18. Weighting and Ranking Based on Compromise Solution with Linear
  19. Assignment Approach; Journal of Civil Engineering and Management, 25(3),
  20. 241–251;
  21. [5] Delgado, A. & Romero, I. (2016), Environmental Conflict Analysis Using
  22. an Integrated Grey Clustering and Entropy-weight Method: A Case Study of
  23. a Mining Project in Peru.Environmental Modelling& Software, 77, 108-121;
  24. [6] Dorfeshan, Y.&Mousavi, S.M. (2019),A Group TOPSIS-COPRAS
  25. Methodology with Pythagorean Fuzzy Sets Considering Weights of Experts
  26. for Project Critical Path Problem;Journal of Intelligent and Fuzzy Systems,
  27. 36(2), 1375-1387;
  28. [7] Ekhtiari, M., Yadegari, E. &Sadidi, G. (2016), Ranking Entrepreneurship
  29. Main Risks in Non-Profit Financial Funds by TODIM Technique under
  30. Grey Conditions (A Case Study in IRAN).Economic Computation &
  31. Economic Cybernetics Studies & Research, 50(3); ASE Publishing;
  32. [8] Gomes, L. F. A. M. (2009), An Application of the TODIM Method to the
  33. Multicriteria Rental Evaluation of Residential Properties.European Journal
  34. of Operational Research, 193(1), 204-211;
  35. [9] Huang, X. & Zhao, T. (2014), Project Selection and Scheduling with
  36. Uncertain Net Income and Investment Cost.Applied Mathematics and
  37. Computation, 247, 61-71;
  38. [10] Jiang, A., Issa, R. R. &Malek, M. (2011), Construction Project Cash Flow
  39. Planning Using the Pareto Optimality Efficiency Network Model.Journal of
  40. Civil Engineering and Management, 17(4), 510-519;
  41. [11] Leach, L. P. (2014), Critical Chain Project Management.Artech House;
  42. [12] Liu, S. & Lin, Y. (2006), Grey Information: Theory and Practical
  43. Applications.Springer Science & Business Media;
  44. [13] Lucko, G. (2013), Supporting Financial Decision-Making Based on Time
  45. Value of Money with Singularity Functions in Cash Flow
  46. Models.Construction Management and Economics, 31(3), 238-253;
  47. [14] Maravas, A. &Pantouvakis, J. P. (2012), Project Cash Flow Analysis in the
  48. Presence of Uncertainty in Activity Duration and Cost.International Journal
  49. of Project Management, 30(3), 374-384;
  50. [15] Mohagheghi, V., Mousavi, S. M. &Vahdani, B. (2017), Analyzing Project
  51. Cash Flow by a New Interval Type-2 Fuzzy Model with an Application to
  52. Construction Industry.Neural Computing and Applications, 28(11), 3393-
  53. 3411;
  54. A New Approach for Multi-Scenario Project Cash Flow Analysis Based on
  55. TODIM and Critical Chain Methods under Grey Uncertainty
  56. _______________________________________________________________
  57. 279
  58. DOI: 10.24818/18423264/54.2.20.16
  59. [16] Mousavi, S.M., Jolai, F., Tavakkoli-Moghaddam, R.&Vahdani, B.
  60. (2013),A Fuzzy Grey Model Based on the Compromise Ranking for Multi-
  61. Criteria Group Decision Making Problems in Manufacturing
  62. Systems;Journal of Intelligent and Fuzzy Systems, 24(4), 819-827;
  63. [17] Mousavi, S.M., Vahdani, B., Tavakkoli-Moghaddam, R.& Tajik, N.
  64. (2014),Soft Computing Based on a Fuzzy Grey Compromise Solution
  65. Approach with an Application to the Selection Problem of Material
  66. Handling Equipment;International Journal of Computer Integrated
  67. Manufacturing, 27(6), 547-569;
  68. [18] Moradi, N., Mousavi, S. M. &Vahdani, B. (2018), An Interval Type-2
  69. Fuzzy Model for Project-earned Value Analysis under Uncertainty. Journal
  70. of Multiple-Valued Logic & Soft Computing, 30(1), 79–103;
  71. [19] Park, H. K., Han, S. H. & Russell, J. S. (2005), Cash Flow Forecasting
  72. Model for General Contractors Using Moving Weights of Cost
  73. Categories.Journal of Management in Engineering, 21(4), 164-172;
  74. [20] San Cristóbal, J. R., Correa, F., González, M. A., de Navamuel, E. D. R.,
  75. Madariaga, E., Ortega, A. &Trueba, M. (2015), A Residual Grey
  76. Prediction Model for Predicting S-Curves in Projects. Procedia Computer
  77. Science, 64, 586-593;
  78. [21] Shash, A. A. &Qarra, A. A. (2018), Cash Flow Management of
  79. Construction Projects in Saudi Arabia.Project Management Journal, 49(5),
  80. 48-63;
  81. [22] Simion, C. P. & Marin, I. (2018), Project Cost Estimate at Completion:
  82. Earned Value Management versus Earned Schedule-Based Regression
  83. Models. A Comparative Analysis of the Models Application in the
  84. Construction Projects in Romania. Economic Computation & Economic
  85. Cybernetics Studies & Research, 52(3); ASE Publishing;
  86. [23] Tavana, M., Khalili-Damghani, K. &Sadi-Nezhad, S. (2013), A Fuzzy
  87. Group Data Envelopment Analysis Model for High-Technology Project
  88. Selection: A Case Study at NASA.Computers & Industrial Engineering,
  89. 66(1), 10-23;
  90. [24] Yu, M. C., Dang, V. L. &Yeh, H. C. (2017), Measuring Cash Flow and
  91. Overdraft for Fuzzy Project Networks with Overlapping Activities.Journal of
  92. Civil Engineering and Management, 23(4), 487-498;
  93. [25] Zhang, W. G., Mei, Q., Lu, Q. & Xiao, W. L. (2011), Evaluating Methods
  94. of Investment Project and Optimizing Models of Portfolio Selection in
  95. Fuzzy Uncertainty.Computers & Industrial Engineering, 61(3), 721-728.

Similar Articles

11-20 of 694

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)