Project Cost Estimate at Completion: Earned Value Management versus Earned Schedule-Based Regression Models. A Comparative Analysis of the Models Application in the Construction Projects in Romania
The Bucharest University of Economic Studies
The Bucharest University of Economic Studies
Abstract
This paper explores the application of CEAC (Cost Estimate at Completion) calculation models for construction projects in Romania. Four models based on Earned Value Management, a GGM (Gompertz Growth) based model, and an E arned Schedule GGM based model were selected. Based on the data analyzed for 30 projects, the percentage error was determined to apply the four EVM models and the two GGMs based on each project. Percentage error for applying ES GGM based models was lower than for EVM models (C ost Performance Index , C omposite Index , C ritical Ratio , M oving Average ). The accuracy and precision of ES -GGM based models have proven superior in all project life cycles compared to EVM models.
References
- [1]Ahiaga-Dagbui, D. D., Love, P. E. D., Smith, S., Ackermann, F. (2017),
- Toward a Systemic View to Cost Overrun Causation in Infrastructure Projects:
- A Review and Implications for Research. Project Management Journal, 48(2),
- 88–98;
- [2]Cantarelli, C., Flyvbjerg, B., Molin, E. J. & van Wee, B. (2010), Cost
- Overruns in Large-Scale Transportation Infrastructure Projects: Explanations
- and their Theoretical Embeddedness. European Journal of Transport
- Infrastructure Research, 10(1), 5–18;
- [3]De Marco, A., Rosso, M., Narbaev, T. (2016b), Nonlinear Cost Estimates at
- Completion Adjusted with Risk Contingency. Journal of Modern Project
- Management, 4(2), 24-33;
- [4]Fleming, Q.W., Koppelman, J.M. (2006), Earned Value Project
- Management, third ed. Project Management Institute, Inc., Newtown Square, PA;
- [5]Ishii, N., Takano, Y. & Muraki, M. (2014), An Order Acceptance Strategy
- under Limited Engineering Man-hours for Cost Estimation in Engineering–
- Procurement–Construction Projects ;International Journal of Project
- Management 32, 519–528;
- [6]Jørgensen, M., Halkjelsvik, T. &Kitchenham, B.(2012), How Does Project
- Size Affect Cost Estimation Error? Statistical Artifacts and Methodological
- Challenges ; International Journal of Project Management 30, 839–849;
- [7] Kim, B.C., Reinschmidt, K.F. (2011), Combination of Project Cost Forecasts
- in Earned Value Management. Journal of Construction Engineering and
- Management137 (11), 958–966;
- [8] Lipke, W. (2004), Independent Estimates at Completion: Another Method.
- Crosstalk. J. Def. Softw. Eng. 26–30 (October);
- [9]Lipke, W. (2003), Schedule is Different . The Measurable News. 31–34
- (Summer);
- [10]Love, P. E. D., Smith, J., Simpson, I., Regan, M. &Olatunji,O.(2015),
- Understanding the Landscape of Overruns in Transport Infrastructure
- Projects. Environment and Planning B: Planning and Design, 42(3);
- [11]Narbaev, T., De Marco, A. (2014), Combination of Growth Model and
- Earned Schedule to Forecast Project Cost at Completion. Journal of Construction
- Engineering and Management. 140 (1);
- [12]Narbaev, T., De Marco, A. (2014), An Earned Schedule Based Regression
- Model to Improve Cost Estimate at Completion. International Journal of Project
- Management., 32(6), 1007-1018;
- [13]PMI (2011), Practice Standard for Earned Value Management, second ed.
- Project Management Institute, Inc., Newtown Square, PA;
- Cezar-Petre Simion, Irinel Marin
- ____________________________________________________________
- DOI: 10.24818/18423264/52.3.18.14
- 216
- [14]Seber, G.A., Wild, C.J. (1989), Nonlinear Regression. John Wiley & Sons;
- New York, NY;
- [15]Simion-Melinte C.(2016), Factors Influencing the Choice of Cost Estimates
- Types and the Accuracy of Estimates for Construction Projects. Proceedings of
- the 10th International Management Conference, "Challenges of Modern
- Management", November 3rd-4th,2016, 50-56;
- [16]Vandevoorde, S., Vanhoucke, M. (2006), A Comparison of Different Project
- Duration Forecasting Methods Using Earned Value Metrics. International
- Journal of Project Management,24 (4), 289–302;
- [17]Yokum, J.T., Armstrong, J.S. (1995), Beyond Accuracy: Comparison of
- Criteria Used to Select Forecasting Methods .Int. J. Forecast. 11 (4), 591–597.