A Multi-Objective Water Cycle Algorithm for the BI-Objective Multi-Mode Project Resource Renting Problem

DOI:
https://doi.org/10.24818/18423264/58.1.24.07
Submitted
October 24, 2026

Abstract

A resource renting problem is a project scheduling problem in which the required resources should be rented, and the goal is to find a schedule and resource renting plan such that the total cost of the resources minimises. Traditionally, the model of a resource renting problem contains single-mode activities and a single objective function. This research aims to present a new mathematical model for a bi -objective multi- mode resource renting problem. The objectives are to minimis e the project makespan and also the total c ost of resources, including the time -independent resource procurement costs and time -dependent resource renting costs, simultaneously. A novel evolutionary algorithm, namely the Multi - Objective Water Cycle Algorithm (MOWCA), is employed to solve this NP-hard problem. In order to evaluate the proposed algorithm, the Non- Dominated Sorting Genetic Algorithm (NSGA-II) is applied, too. A set of instances is selected from the digital library of project scheduling problems to analyse the performances of evolutionary algorithms. The results of the experimentation are quite satisfactory.

References

  1. [1] Afshar-Nadjafi, B., Basati, M., Maghsoudlou, H. (2017) , Project scheduling for
  2. minimizing temporary availability cost of rental resources and tardiness penalty of
  3. activities. Applied Soft Computing, 61, 536-548.
  4. [2] Arjmand, M., Najafi, A.A., Ebrahimzadeh M. (2020) , Evolutionary algorithms for
  5. multi-objective stochastic resource availability cost problem. OPSEARCH, 57(3),
  6. 935-985.
  7. [3] Ballestín, F. (2007) , A Genetic Algorithm for the Resource Renting Problem with
  8. Minimum and Maximum Time Lags. Evolutionary Computation i n Combinatorial
  9. Optimization, 25-35.
  10. [4] Deb, K., Pratap, A., Agarwal, S., Meyarivan, T. (2002), A fast and elitist multiobjective
  11. genetic algorithm : NSGA-II, IEEE Transactions on Evolutionary Computation, 6(2),
  12. 182-197.
  13. [5] Eskandar, H., Sadollah, A., Bahreininejad A., Hamdi, M. (2012), Water cycle algorithm
  14. - a novel metaheuristic optimization method for solving constrained engineering
  15. optimization problems. Computers & Structures, 110-111, 151-160.
  16. [6] Hartmann, S., Briskorn, D. (2022), An updated survey of variants and extensions of the
  17. resource-constrained project scheduling problem. European Journal of Operational
  18. Research, 297(1), 1-14.
  19. [7] Kerkhove, L., Vanhoucke, M., Maenhout, B. (2017) , On the resource renting problem
  20. with overtime. Computers & Industrial Engineering, 111, 303-319.
  21. [8] Khalili S, Najafi AA, Niaki S .T.A. (2013), Bi-objective Resource Constrained Project
  22. Scheduling Problem with Makespan and Net Present Value Criteria: Two Meta-
  23. Heuristic Algorithms, International Journal of Advanced Manufacturing Technology,
  24. 69, 617-626.
  25. [9] Nabipoor Afruzi, E., Aghaie, A., Najafi, A. (2020) , Robust optimization for the
  26. resource-constrained multi -project scheduling problem with uncertain activity
  27. durations. Scientia Iranica, 27(1), 361-376.
  28. A Multi-Objective Water Cycle Algorithm…
  29. Vol. 58, Issue 1/2024 119
  30. [10] Najafi, AA., Azimi, F. (2009), A Priority Rule-Based Heuristic for Resource Investment
  31. Project Scheduling Problem with Discounted Cash Flows and Tardiness Penalties.
  32. Mathematical Problems in Engineering, 2009, 1-10.
  33. [11] Nübel, H. (2001) , The resource renting problem subject to temporal constraints . OR-
  34. Spektrum, 23(3), 359-381.
  35. [12] Rezaei, F., Najafi, A.A., Ramezanian, R., (2020), Mean-conditional value at risk model
  36. for the stochastic project scheduling problem, Computers and Industrial Engineering,
  37. 142, 106356.
  38. [13] Sadollah, A., Eskandar, H., Kim, J. (2015), Water cycle algorithm for solving constrained
  39. multi-objective optimization problems. Applied Soft Computing, 27, 279-298.
  40. [14] Schnabel, A., Kellenbrink, C., Helber, S. (2018) , Profit-oriented scheduling of
  41. resource-constrained projects with flexible capacity constraints. Business Research, 11,
  42. 329-356.
  43. [15] Servranckx, T., Coelho, J., Vanhoucke, M. (2022 ), Various extensions in resource -
  44. constrained project scheduling with alternative subgraphs. International Journal of
  45. Production Research, 60(11), 3501-3520.
  46. [16] Shahsavar M., Najafi A.A. , Niaki, S.T.A. (2011) , Statistical Design of Genetic
  47. Algorithms for Combinatorial Optimization Problems ", Mathematical Problems in
  48. Engineering, 2011, 2-17.
  49. [17] Siamakmanesh, N., Najafi, A.A., Azimi, F. (2022) , A Work-content Based Resource
  50. Availability Cost Problem: Mathematical Modeling and Solving Procedure . Economic
  51. Computation and Economic Cybernetics Studies and Research, 56(1), 75-90.
  52. [18] Vandenheede, L., Vanhoucke, M., Maenhout, B. (2016) , A scatter search for the
  53. extended resource renting problem. International Journal of Production Research,
  54. 54(16), 4723-4743.

Similar Articles

1-10 of 426

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)