Does Preemption Lead to More Leveled Resource Usage in Projects? A Computational Study Based on Mixed-Integer Linear Programming

DOI:
https://doi.org/10.24818/18423264/53.4.19.15
Submitted
October 24, 2026

Abstract

As an effective project resource scheduling technique, resource leveling has been extensively investigated. A common assumption in this technique is that activities are not allowed to be interrupted during execution. Little attentions have been paid to the preemptive resource leveling problem (PRLP) in the literature. However, preemption is often adopted in project management practice. In this paper, we discuss whether preemption leads to more leveled resource usage in projects. We propose a mixed-integer linear programming model for the PRLP . Computational experiments are performed on a large number of randomly generated instances to verify the improvement gained by incorporating preemptionto the RLP . Additionally, a real-world case study is used to further illustrate whe ther preemptionimproves resource leveling in practical project management.

References

  1. [1] Ballestín, F., Schwindt, C., Zimmermann, J., Ballestín, F.& Zimmermann, J.
  2. (2007),Resource Leveling In Make-To-Order Production: Modeling and
  3. Heuristic Solution Method. International Journal of Operations Research, 4(1),
  4. 50-62;
  5. [2] Bandelloni, M., Tucci, M. &Rinaldi, R. (1994),Optimal Resource Leveling
  6. Using Non-Serial Dynamic Programming. European Journal of Operational
  7. Research, 78(2), 162-177;
  8. [3] Burgess, A. R. &Killebrew, J. B. (1962),V ariation in Activity Level on a Cyclical
  9. Arrow Diagram. Journal of Industrial Engineering, 13(2), 76-83;
  10. Does Preemption Lead to More Leveled Resource Usage in Projects?
  11. A Computational Study Based on Mixed-Integer Linear Programming
  12. 257
  13. DOI: 10.24818/18423264/53.4.19.15
  14. [4] Christodoulou, S. E., Ellinas, G. &Michaelidou-Kamenou, A. (2010),Minimum
  15. Moment Method for Resource Leveling Using Entropy Maximization. Journal of
  16. Construction Engineering and Management, 136(5), 518-527;
  17. [5] Demeulemeester, E. L.&Herroelen, W. S. (2002), Project Scheduling: A
  18. Research Handbook.New York: Kluwer Academic;
  19. [6] Demeulemeester, E., Vanhoucke, M.&Herroelen, W. (2003), RanGen: A
  20. Random Network Generator for Activity-on-the-Node Networks. Journal of
  21. scheduling, 6(1), 17-38;
  22. [7] Dobrovolskienė, N. &Tamošiūnienė, R. (2016), Sustainability-oriented
  23. Financial Resource Allocation in a Project Portfolio through Multi-criteria
  24. Decision-making. Sustainability, 8(5), 485;
  25. [8] Doulabi, S. H. H., Seifi, A.&Shariat, S. Y. (2011),An Efficient Hybrid Genetic
  26. Algorithm for Resource Leveling via Activity Splitting. Journal of Construction
  27. Engineering and Management, 137(2), 137-146;
  28. [9] Gather, T., Zimmermann, J. & Bartels, J. H. (2011),Exact Methods for the
  29. Resource Leveling Problem. Journal of Scheduling, 14(6), 557-569;
  30. [10] Hariga, M. & El-Sayegh, S. M. (2011),Cost Optimization Model for the
  31. Multi-resource Leveling Problem with Allowed Activity Splitting. Journal of
  32. Construction Engineering and Management, 137(1), 56-64;
  33. [11] Koulinas, G. K.&Anagnostopoulos, K. P. (2013), A New Tabu Search-based
  34. Hyper-heuristic Algorithm for Solving Construction Leveling Problems with
  35. Limited Resource Availabilities.Automation in Construction, 31(3), 169-175;
  36. [12] Kreter, S., Rieck, J. & Zimmermann, J. (2014),The Total Adjustment Cost
  37. Problem: Applications, Models, and Solution Algorithms. Journal of Scheduling,
  38. 17(2), 145-160;
  39. [13] Li, H. &Demeulemeester, E. (2016),A Genetic Algorithm for the Robust
  40. Resource Leveling Problem. Journal of Scheduling, 19(1), 43-60;
  41. [14] Li, H. & Dong, X. (2018),Multi-mode Resource Leveling in Projects with
  42. Mode-dependent Generalized Precedence Relations. Expert Systems with
  43. Applications, 97, 193-204;
  44. [15] Li, H., Xiong, L., Liu, Y.& Li, H. (2018a),An Effective Genetic Algorithm for
  45. the Resource Leveling Problem with Generalised Precedence Relations.
  46. International Journal of Production Research, 56(5), 2054-2075;
  47. [16] Li, H., Xu, Z.& Wei, W. (2018b),Bi-Objective Scheduling Optimization for
  48. Discrete Time/Cost Trade-Off in Projects. Sustainability, 10(8), 2802;
  49. Yinbin Liu, Ziyi Hu, Hongbo Li, Hongli Zhu
  50. 258
  51. DOI: 10.24818/18423264/53.4.19.15
  52. [17] Li, H., Xu, Z.&Demeulemeester, E. (2014),Scheduling Policies for the
  53. Stochastic Resource Leveling Problem. Journal of Construction Engineering and
  54. Management, 141(2), 04014072;
  55. [18] Ma, G., Gu, L. & Li, N. (2015),Scenario-based Proactive Robust Optimization
  56. for Critical-chain Project Scheduling. Journal of Construction Engineering and
  57. Management, 141(10), 04015030;
  58. [19] Mehdizadeh, E. &Akbari, H. (2017),A Novel Vibration Damping Optimization
  59. Algorithm for Resource Constrained Multi-project Scheduling Problem.
  60. Economic Computation and Economic Cybernetics Studies and Research, 51(2);
  61. ASE Publishing;
  62. [20] Mehdizadeh, E. & Dadgar, S. N. (2014);Using Vibration Damping Optimization
  63. Algorithm for Resource Constraint Project Scheduling Problem with Weighted
  64. Earliness-Tardiness Penalties and Interval Due Dates. Economic Computation
  65. and Economic Cybernetics Studies and Research, 48(1); ASE Publishing;
  66. [21] Nadjafi, B. (2014),Using Grasp for Resource Availability Cost Problem with
  67. Time Dependent Resource Cost. Economic Computation and Economic
  68. Cybernetics Studies & Research, 48(1), 201-215; ASE Publishing;
  69. [22] Nadjafi, B., Khalaj, Z. & Mehdizadeh, E. (2013), A Branch and Bound
  70. Approach to Solve the Preemptive Resource Leveling Problem. International
  71. Journal of Manufacturing Engineering, (1), 24-26;
  72. [23] Neumann K., Schwindt C.& Zimmermann J. (2003),Project Scheduling with
  73. Time Windows and Scarce Resources: Temporal and Resource-constrained
  74. Project Scheduling with Regular and Nonregular Objective Functions. Springer;
  75. [24] Neumann, K. & Zimmermann, J. (1999), Resource Leveling for Projects with
  76. Schedule-dependent Time Windows. European Journal of Operational Research,
  77. 117(3), 591-605;
  78. [25] Ranjbar, M. (2013),A Path-relinking Metaheuristic for the Resource Leveling
  79. Problem.Journal of the Operational Research Society, 64(7), 1071-1078;
  80. [26] Rieck, J.& Gather, T. (2012). Mixed-integer Linear Programming for Resource
  81. Leveling Problems. European Journal of Operational Research, 221(1), 27-37;
  82. [27] Son, J. &Mattila, K. G. (2004),Binary Resource Leveling Model: Activity
  83. Splitting Allowed. Journal of Construction Engineering and Management, 130(6),
  84. 887-894.

Similar Articles

1-10 of 477

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)