Using Vibration Damping Optimization Algorithm for Resource Constraint Project Scheduling Problem with Weighted Earliness-Tardiness Penalties and Interval Due Dates

Submitted
October 24, 2026

Abstract

Resource constrained project scheduling problem with weighted earliness-tardiness penalties is one of the most crucial problems in resource constrained project scheduling problems. This paper focuses on the notable characteristic of the model which is an interval due dates for activities. In this problem setting, act ivities have an interval activity due date with associated unit earliness and tardiness penalties. Vibration damping optimization (VDO) is proposed to solve this strongly NP -hard model. The proposed VDO algorithm is computationally compared with simulated annealing (SA) algorithm and the results are analyzed and discussed. Response surface methodology (RSM) is employed to tune of the VDO and SA parameters.

References

  1. [1] Afshar-Nadjafi, B. and Shadrok, Sh. (2008), An Algorithm for the
  2. Weighted Earliness- Tardiness Unconstrained Project scheduling Problem;
  3. Journal of Applied Sciences: 1651-1659;
  4. [2] Boctor, F. F. (1996), Resource-constrained Project Scheduling by Simulated
  5. Annealin; International Journal of Production Research 34 2335–2351;
  6. [3] Bouleimen, K. and Lecocq, H. (2003), A New Efficient Simulated
  7. Annealing Algorithm for the Resource Constrained Project Scheduling
  8. Problem and its Multiple Mode Version; European Journal of Operational
  9. Research: 149, 268–281;
  10. Using VDO Algorithm for RCPSPWET and Interval Due Dates
  11. _______________________________________________________________
  12. [4] Demeulemeester, E., Vanhoucke, M. and Herroelen, W. (2003), Rangen:
  13. A Random Network Generator for Activity-on-the Node Networks; Journal
  14. of Scheduling;
  15. [5] Demeulemeester, E. and Herroelen, W. (2002), Project Scheduling - A
  16. Research Hand Book; Katholieke University Leuven;
  17. [6] Demeulemeester, E. L. (1992), Optimal Algorithms for Various Classes of
  18. Multiple Resource-Constrained Project Scheduling Problem; Ph.D thesis,
  19. Department of Applied Economics, Katholieke Universiteit Leuven, Belgium;
  20. [7] Elmaghraby, S. E. (2005), On the Fallacy of Averages in Project Risk
  21. Management; European Journal of Operational Research, 165 (2), 307–313;
  22. [8] Herroelen W. S, Van Dommelen, P. and Demeulemeester, E. L. (1997),
  23. Project Network Models with Discounted Cash Flows- A Guide Tour
  24. through Recent Developments; European journal of Operational Research,
  25. 100(1), 97-121;
  26. [9] Icemeli, O. and Erenguc, S. S. (1996), A Branch & Bound Procedure for
  27. the Resource-Constrained Project Scheduling Problem with Discounted
  28. Cash Flows; Management science, 42, 1395-1408;
  29. [10] Kelley, J. E. (1963), The Critical-path Method: Resources planning and
  30. scheduling; In: Industrial scheduling, Muth, J. F. and G. L. Thompson (eds.),
  31. Prentice-Hall, Englewood Cliffs, NJ, 347-365;
  32. [11] Kirk Patrick, S., Gellat, C. D, and Vecchi, M. P. (1983), Optimization by
  33. Simulated Annealing; Science: 671 – 680;
  34. [12] Kogan, K. and Shtub, A. (1999), Theory and Methodology Scheduling
  35. Projects with Variable-intensity Activities: The case of dynamic earliness
  36. and tardiness costs; European Journal of Operational Research, 118, 65-80;
  37. [13] Khoshjahan, Y., Najafi, A. A. and Afshar-Nadjafi, B. (2013), Resource
  38. Constrained Project Scheduling Problem with Discounted Earliness–
  39. tardiness Penalties: Mathematical modeling and solving procedure.
  40. Computers & Industrial Engineering, 66(2), 293-300;
  41. [14] Lawrence, S. R., Morton, T. E. (1993), Resource-constrained Multi-
  42. project Scheduling with Tardy Costs: Comparing Myopic Bottleneck and
  43. Resource Pricing Heuristics; European Journal of Operational Research, 64,
  44. 168–187;
  45. [15] Mehdizadeh E. and Tavakkoli-Moghaddam R. (2009), Vibration
  46. Damping Optimization Algorithm for an Identical Parallel-machines
  47. Scheduling Problem; In: The 2nd International Conference of Iranian
  48. Operations Research Society, Babolsar, Iran, PP. 216-219;
  49. [16] Mendes, J. J. M. (2003), Sistema de apoio a` decisa˜o para planeamento
  50. de sistemas de produc¸a˜o do tipo project,. PhD thesis, Departamento de
  51. Engenharia Mecaˆnica e Gesta˜o Industrial, Faculdade de Engenharia da
  52. Universidade do Porto, Porto, Portugal;
  53. Esmaeil Mehdizadeh, Siamak Nezhad Dadgar
  54. __________________________________________________________________
  55. [17] Metropoli, N., Rosenbluth, A., Rosenbluth M., Teller, A. and Teller, E.
  56. (1953), Equation of State Calculations by fast Computing Machines;
  57. Journal of Chemical Physics 21, 1087–1092;
  58. [18] Mika, M., Walig_ora, G. and Wezglarz, J. (2005), Simulated Annealing
  59. and Tabu Search for Multi-mode Resource-constrained Project Scheduling
  60. with Positive Discounted Cash Flows and Different Payment Models;
  61. European Journal of Operational Research, 164, 639–668;
  62. [19] Myers Raymond, H. and Montgomery, D. C. (2002), Response Surface
  63. Methodology: Process and Product Optimization Using Designed
  64. Experiment; A Wiley-Interscience Publication;
  65. [20] Shadrokh, Sh. and Kianfar, F. (2007), A Genetic Algorithm for Resource
  66. Investment Project Scheduling Problem, Tardiness Permitted with Penalty,
  67. European Journal of Operational Research, 181, 86–101;
  68. [21] Vanhoucke, M. (2001), Exact Algorithms for Various Types of Project
  69. Scheduling Problem Non-regular Objectives and Time/Cost tradeoffs;
  70. Unpublished Ph.D . Dissertation, Katholieke University Leuven;
  71. [22] Vanhoucke, M., Demeulemeester, E. and Herroelen, W. (2000),
  72. Maximizing the Net Present Value of a Project with Progress Payments;
  73. Research Report 0028. Department of Applied Economics, Katholieke
  74. Universiteit Leuven;
  75. [23] Vanhoucke, M., Demeulemeester, E. and Herroelen, W. (1999), An
  76. Exact Procedure for the Resource-Constrained Weighted Earliness-
  77. Tardiness Project Scheduling Problem; Operations Management Group,
  78. Department of Applied Economics;
  79. [24] Vanhoucke, M , Demeulemeester , E and Herroelen,W , (2001), An
  80. Exact Procedure for the Resource-Constrained Weighted Earliness-
  81. Tardiness Project Scheduling Problem . Operations Management Group,
  82. Department of Applied Economics, Katholieke Universiteit Leuven,
  83. Naamsestraat 69, B-3000 Leuven, Belgium;
  84. [25] Vanhoucke, M., Demeulemeester, E. and Herroelen, W. (2003), Discrete
  85. Optimization Progress Payments in Project Scheduling Problems; European
  86. Journal of Operational Research, 148, 604–620;
  87. [26] WooK, K., Yunb, Y., S, Yoonc J. M., Gend, M., Yamazakia, G. (2005),
  88. Hybrid Genetic Algorithm with Adaptive Abilities for Resource-constrained
  89. Multiple Project Scheduling, Computers in Industry, 56, 143–160.

Similar Articles

1-10 of 313

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)